      Potash Loader

      Industrial
        Project Details

        Potash Loader

        Two potash loaders were consecutively scaffolded inside and out for cleaning and painting. An irregular shape with very few straight lines were this project’s challenges. Oh, and a four day period in which to build within. Matakana completed each loader in three days, gaining for our customer a much needed extra day on each of these time sensitive shut downs.